1-05.4 Conformity With & Deviations From Plans & Stakes
Delete this Section and replace it with the following:
1-05.4 Pre-Construction Survey
(PUD July 2020)
The Contractor shall obtain the services of a professional surveyor licensed in the State of Washington to perform pre-construction surveying. Pre-construction surveying consists of setting lines and grades for the proposed work. At a minimum, the pre-construction survey shall establish hubs / stakes as follows:
Pre-Construction Survey Item | Horizontal Tolerence | Vertical Tolerence |
---|---|---|
Valves* | ± 0.1 foot | ± 0.1 foot |
Fittings* | ± 0.1 foot | ± 0.1 foot |
Fire Hydrants | ± 0.1 foot | ± 0.1 foot |
Water Main (50 inch intervals maximum) | ± 0.1 foot | ± 0.1 foot |
*Valve / fitting clusters only require a single survey reference
Following the pre-construction survey, but prior to construction, the Contractor shall place paint marks on the ground of the intended water main alignment and coordinate a time to meet with the Engineer to walk the project site and discuss the proposed Work.
1-05.7 Removal of Defective & Unauthorized Work
(October 1, 2005 APWA GSP)
Supplement this section with the following:
If the Contractor fails to remedy defective or unauthorized work within the time specified in a written notice from the Engineer, or fails to perform any part of the work required by the Contract Documents, the Engineer may correct and remedy such work as may be identified in the written notice, with Contracting Agency forces or by such other means as the Contracting Agency may deem necessary.
If the Contractor fails to comply with a written order to remedy what the Engineer determines to be an emergency situation, the Engineer may have the defective and unauthorized work corrected immediately, have the rejected work removed and replaced, or have work the Contractor refuses to perform completed by using Contracting Agency or other forces. An emergency situation is any situation when, in the opinion of the Engineer, a delay in its remedy could be potentially unsafe, or might cause serious risk of loss or damage to the public.
Direct or indirect costs incurred by the Contracting Agency attributable to correcting and remedying defective or unauthorized work, or work the Contractor failed or refused to perform, shall be paid by the Contractor. Payment will be deducted by the Engineer from monies due, or to become due, the Contractor. Such direct and indirect costs shall include in particular, but without limitation, compensation for additional professional services required, and costs for repair and replacement of work of others destroyed or damaged by correction, removal, or replacement of the Contractor’s unauthorized work.
No adjustment in Contract Time or compensation will be allowed because of the delay in the performance of the work attributable to the exercise of the Contracting Agency’s rights provided by this Section.
The rights exercised under the provisions of this section shall not diminish the Contracting Agency’s right to pursue any other avenue for additional remedy or damages with respect to the Contractor’s failure to perform the work as required.
1-05.10 Guarantees
(PUD November 2020)
Section 1-05.10 is supplemented with the following:
The Work shall meet the requirements of the Contract Documents. Prior to 1 year following the date of Substantial Completion, the PUD will conduct an inspection. If defects are found by the PUD, the Contractor shall return to the project and repair or replace all defects in workmanship and material without charge to the PUD. Items required to be repaired shall have a renewed warranty following the acceptance of the correction of the defects. The renewed warranty shall be in writing and addressed to the PUD.
The Contractor shall start work to remedy any such defects within 14 calendar days of receiving Contracting Agency’s written notice of a defect, and shall complete such work within the time stated in the Contracting Agency’s notice. In case of an emergency, where damage may result from delay or where loss of services may result, such corrections may be made by the Contracting Agency’s own forces or another contractor, in which case the cost of corrections shall be paid by the Contractor. In the event the Contractor does not accomplish corrections within the time specified, the work will be otherwise accomplished and the cost of same shall be paid by the Contractor.
This obligation to return to the project and correct defects or failure of performance is in addition to all other warranties and obligations under the terms of the Contract including but not limited to manufacturer’s warranties and the Contractor’s warranty and obligation that the work performed and materials supplied meet or exceed the quality and performance required by the Contract Documents.
1-05.11 Final Inspection
Delete this section and replace it with the following:
1-05.11 Final Inspections and Operational Testing
(October 1, 2005 APWA GSP)
1-05.11(1) Substantial Completion Date
When the Contractor considers the work to be substantially complete, the Contractor shall so notify the Engineer and request the Engineer establish the Substantial Completion Date. The Contractor’s request shall list the specific items of work that remain to be completed in order to reach physical completion. The Engineer will schedule an inspection of the work with the Contractor to determine the status of completion. The Engineer may also establish the Substantial Completion Date unilaterally.
If, after this inspection, the Engineer concurs with the Contractor that the work is substantially complete and ready for its intended use, the Engineer, by written notice to the Contractor, will set the Substantial Completion Date. If, after this inspection the Engineer does not consider the work substantially complete and ready for its intended use, the Engineer will, by written notice, so notify the Contractor giving the reasons therefore.
Upon receipt of written notice concurring in or denying substantial completion, whichever is applicable, the Contractor shall pursue vigorously, diligently and without unauthorized interruption, the work necessary to reach Substantial and Physical Completion. The Contractor shall provide the Engineer with a revised schedule indicating when the Contractor expects to reach substantial and physical completion of the work.
The above process shall be repeated until the Engineer establishes the Substantial Completion Date and the Contractor considers the work physically complete and ready for final inspection.
1-05.11(2) Final Inspection and Physical Completion Date
When the Contractor considers the work physically complete and ready for final inspection, the Contractor by written notice, shall request the Engineer to schedule a final inspection. The Engineer will set a date for final inspection. The Engineer and the Contractor will then make a final inspection and the Engineer will notify the Contractor in writing of all particulars in which the final inspection reveals the work incomplete or unacceptable. The Contractor shall immediately take such corrective measures as are necessary to remedy the listed deficiencies. Corrective work shall be pursued vigorously, diligently, and without interruption until physical completion of the listed deficiencies. This process will continue until the Engineer is satisfied the listed deficiencies have been corrected.
If action to correct the listed deficiencies is not initiated within 7 days after receipt of the written notice listing the deficiencies, the Engineer may, upon written notice to the Contractor, take whatever steps are necessary to correct those deficiencies pursuant to Section 1-05.7.
The Contractor will not be allowed an extension of Contract Time because of a delay in the performance of the work attributable to the exercise of the Engineer’s right hereunder.
Upon correction of all deficiencies, the Engineer will notify the Contractor and the Contracting Agency, in writing, of the date upon which the work was considered physically complete. That date shall constitute the Physical Completion Date of the contract, but shall not imply acceptance of the work or that all the obligations of the Contractor under the contract have been fulfilled.
1-05.11(3) Operational Testing
It is the intent of the Contracting Agency to have at the Physical Completion Date a complete and operable system. Therefore when the work involves the installation of machinery or other mechanical equipment; street lighting, electrical distribution or signal systems; irrigation systems; buildings; or other similar work it may be desirable for the Engineer to have the Contractor operate and test the work for a period of time after final inspection but prior to the physical completion date. Whenever items of work are listed in the Contract Provisions for operational testing they shall be fully tested under operating conditions for the time period specified to ensure their acceptability prior to the Physical Completion Date. During and following the test period, the Contractor shall correct any items of workmanship, materials, or equipment which prove faulty, or that are not in first class operating condition. Equipment, electrical controls, meters, or other devices and equipment to be tested during this period shall be tested under the observation of the Engineer, so that the Engineer may determine their suitability for the purpose for which they were installed. The Physical Completion Date cannot be established until testing and corrections have been completed to the satisfaction of the Engineer.
The costs for power, gas, labor, material, supplies, and everything else needed to successfully complete operational testing, shall be included in the unit contract prices related to the system being tested, unless specifically set forth otherwise in the proposal.
Operational and test periods, when required by the Engineer, shall not affect a manufacturer’s guaranties or warranties furnished under the terms of the contract.
1-05.13 Superintendents, Labor and Equipment of Contractor
(August 14, 2013 APWA GSP)
Delete the 6th and 7th paragraphs of this section.
1-05.15 Method of Serving Notices
(March 25, 2009 APWA GSP)
Revise the second paragraph to read:
All correspondence from the Contractor shall be directed to the Project Engineer. All correspondence from the Contractor constituting any notification, notice of protest, notice of dispute, or other correspondence constituting notification required to be furnished under the Contract, must be in paper format, hand delivered or sent via mail delivery service to the Project Engineer's office. Electronic copies such as e-mails or electronically delivered copies of correspondence will not constitute such notice and will not comply with the requirements of the Contract.
Add the following new sections:
1-05.16 Water and Power
(October 1, 2005 APWA GSP)
The Contractor shall make necessary arrangements and shall bear the costs for power and water necessary for the performance of the work, unless the contract includes power and water as a pay item.
1-05.17 As-Built Drawings
(PUD April 2020)
The Contractor shall maintain one set of full-size plans for As-Built Drawings, updated with clear and accurate red-lined field revisions on a daily basis, and within 2 business days after receipt of information that a change in Work has occurred. The Contractor shall not conceal any work until the required information is recorded.
This As-Built Drawing set shall be used for this purpose alone, shall be kept separate from other Plan sheets, and shall be clearly marked as As-Built Drawings. These As-Built Drawings shall be kept on site at the Contractor’s field office and shall be available for review by the Contracting Agency at all times. The Contractor shall bring the As-Built Drawings to each progress meeting for review.
The preparation and upkeep of the As-Built Drawings is to be the assigned responsibility of a single, experienced, and qualified individual. The quality of the As-Built Drawings, in terms of accuracy, clarity, and completeness, is to be adequate to allow the Contracting Agency to modify the computer-aided drafting (CAD) Contract Drawings to produce a complete set of Record Drawings for the Contracting Agency without further investigative effort by the Contracting Agency.
The As-Built Drawing markups shall document all changes in the Work, both concealed and visible. Items that must be shown on the markups include but are not limited to:
- Actual dimensions, arrangement, and materials used when different than shown in the Plans.
- Changes made by Change Order or Field Order.
- Changes made by the Contractor.
- Accurate locations of storm sewer, sanitary sewer, water mains and other water appurtenances, structures, conduits, light standards, vaults, width of roadways, sidewalks, landscaping areas, building footprints, channelization and pavement markings, etc. Include pipe invert elevations, top of castings (manholes, inlets, etc.).
Making Entries on the As Built Drawings:
- Use erasable colored pencil (not ink) for all markings on the Record Drawings, conforming to the following color code:
- Additions - Red
- Deletions - Green
- Comments - Blue
- Dimensions - Graphite
- Provide the applicable reference for all entries, such as the change order number, the request for information (RFI) number, or the approved shop drawing number.
- Date all entries.
- Clearly identify all items in the entry with notes similar to those in the Contract Drawings (such as pipe symbols, centerline elevations, materials, pipe joint abbreviations, etc.).
The Contractor shall certify on the As-Built Drawings that said drawings are an accurate depiction of built conditions and in conformance with the requirements detailed above. The Contractor shall submit final Record Drawings to the Contracting Agency. Contracting Agency acceptance of the Record Drawings is one of the requirements for achieving Physical Completion.
Payment will be made for the following bid item:
As-Built Drawings | Lump Sum |
---|---|
(Minimum Bid $1,000) |
Payment for this item will be made on a prorated monthly basis for work completed in accordance with this section up to 75% of the lump sum bid. The final 25% of the lump sum item will be paid upon submittal and approval of the completed As-Built Drawings set prepared in conformance with these Special Provisions.
A minimum bid amount has been entered in the Bid Proposal for this item. The Contractor must bid at least that amount.