2-02.1 Description
(PUD July 2020)
Section 2-02.1 is supplemented with the following:
This Work also includes removing and disposing of, or salvaging, existing vaults, and other structures as shown on the Plans. The Work also includes the backfilling of trenches, holes, or pits that result from such removal.2-02.5 Payment
(PUD July 2020)
Section 2-02.5 is supplemented with the following:
“Removal of _______”, each.
The unit Contract price per each for removal of structures of the kind specified shall be full pay for all costs in connection with removing, disposing of, or salvaging the materials as shown on the Plans, and backfilling of trenches, holes, or pits that result from such removal.