8-01.4 Measurement
(PUD April 2020)
Supplement this section with the following:
No specific unit of measurement will apply to the lump sum item of “Erosion Control and Water Pollution Control”.
8-01.5 Payment
(PUD April 2020)
Supplement this section with the following:
“Erosion Control and Water Pollution Control”, lump sum.
The lump sum Contract payment shall be full compensation for maintenance and removal of erosion and water pollution control devices including removal and disposal of sediment, stabilization and rehabilitation of soil disturbed by these activities, and any additional Work deemed necessary by the Engineer to control erosion and water pollution.