8-02.1 Description
(PUD April 2020)
Section 8-02.1 is supplemented as follows:
This Work consists of in-kind restoration of all disturbed areas between the edge of pavement or curb, and the limits of construction.
8-02.4 Measurement
(PUD April 2020)
Supplement this section with the following:
When the Bid Proposal contains the item “Roadside Restoration” there will be no measurement of unit items for Work defined in Section 8-02.
No specific unit of measurement will apply to the lump sum item of “Roadside Restoration.”
8-02.5 Payment
(PUD April 2020)
Supplement this section with the following:
“Roadside Restoration”, lump sum.
The lump sum Contract payment shall be full compensation for all costs incurred by the Contractor in performing the Contract Work defined in Section 8-02.