8-02 Roadside Restoration

8-02.1 Description

(PUD April 2020)

Section 8-02.1 is supplemented as follows:

This Work consists of in-kind restoration of all disturbed areas between the edge of pavement or curb, and the limits of construction.

8-02.4 Measurement

(PUD April 2020)

Supplement this section with the following:

When the Bid Proposal contains the item “Roadside Restoration” there will be no measurement of unit items for Work defined in Section 8-02.

No specific unit of measurement will apply to the lump sum item of “Roadside Restoration.”

8-02.5 Payment

(PUD April 2020)

Supplement this section with the following:

“Roadside Restoration”, lump sum.

The lump sum Contract payment shall be full compensation for all costs incurred by the Contractor in performing the Contract Work defined in Section 8-02.