A residential project requiring 2 or more transformers will require the following:
- All parcels are staked out.
- All primary electrical equipment (i.e., junction boxes, transformers, etc.) will require a formal Request for Quote that will be submitted from Skamania PUD to its vendors.
- Once quotes have arrived for the electrical equipment, pre-payment must be made before equipment will be ordered.
- Customers are not allowed to purchase transformers from other vendors, only the PUD can purchase transformers needed for a project.
- Project may be subject to an engineering study fee which requires a $500 deposit. Customer is responsible for paying the balance of the engineering study.
Note: Due to supply issues, the PUD is not responsible for changes in cost and delivery time for electrical equipment.